Archer City council approves change order for water project
The Archer City Council approved a change order in the amount of $23,800 for the American Rescue Plan Act water line project during its council meeting on Thursday, April 20.
City Administrator George Huffman said the city's engineering firm did not start from the correct point on E. Walnut which resulted in the city being 280 feet short on eight-inch water lines. Huffman said it costs the city …